Register now or log in to join your professional community.
to prospective clients. You will do which of the following at your next stakeholder project status meeting?
A. Report on the progress of the demo, and note that it's a completed task.
B. Preview the demo for stakeholders, and obtain their approval and sign-off.
C. Review the technical documentation of the demo, and obtain approval and sign-off.
D. Report that the demo has been noted as a completed task in the information retrieval system.
B. is the correct answer. Preview the demo
In my opinion
A. Report on the progress of the demo, and note that it's a completed task
I prefer to with option - B and thanks for the invite.
My answer is Option B which is more convenient to get approval and satisfaction of the stakeholders.
B. Preview the demo for stakeholders, and obtain their approval and sign-off.