A. Is the same since baseline schedules cannot change once the development phase is completed.
B. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
C. Is amended to reflect the scope change, but the original baseline is still maintained for post project review.
D. Now becomes the new schedule, including the changes, and the original baseline is disregarded.
Agreed with Mr. Ayoub Tartir Answer - C
C. Is amended to reflect the scope change, but the original baseline is still maintained for post project review.
Thanks for invit
Option C
Definitely C. It should be ammended to complement the addidtional activity but with consideration for review to determine any effects in the previous baseline.
In my opinion option - C is most appropriate .