Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The two closing procedures are called?

 

A. Contract close out and Verify Scope

B. Project closure and lessons learned

C. Contract close out and administrative closure

D. Project closure and product verification

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/28
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is option C - Contarct closeout & Administrative closure & thanks for the invite.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the right choice

C. Contract close out and administrative closure --------

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

C. Contract close out and administrative closure

More Questions Like This