Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and?

assignable causes.  Under which of the following circumstances should a QC manager consider this type chart

A. Both1) When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process, and2) When a process is subject to constant but stable tool wear.

B. When a process is subject to constant but stable tool wear.

C. When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process

D. When the number of samples outside the current control chart limits become too costly and

cumbersome to investigate.

E. Both1) When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process, and2) When the number of samples outside the current control. chart limits become too costly and cumbersome to investigate..

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/28
Mohamed Kamal
by Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

i think (E) is more suitable and is the answer

Hatim Elamin AbdEllatief Abdedaem
by Hatim Elamin AbdEllatief Abdedaem , DIrector of industry adminstration at Gezira state , ministry of finance and economic affairs Gezira state

Control charts have two general uses in an improvement project. The most common application is as a tool to monitor process stability and control. A less common, although some might argue more powerful, use of control charts is as an analysis tool. The descriptions below provide an overview of the different types of control charts to help practitioners identify the best chart for any monitoring situation, followed by a description of the method for using control charts for analysis.

 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite but I am not able to answer it.

Haytham Bassuony Abdelsalam Elsaied
by Haytham Bassuony Abdelsalam Elsaied , Lab Chemist (Shift In-charge) , Methanex Corporation

E is close to the right answer 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

A. Both1) When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process, and2) When a process is subject to constant but stable tool wear

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.

E. Both1) When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process, and2) When the number of samples outside the current control. chart limits become too costly and cumbersome to investigate..

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

Agree Answer Option E