Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Adjusting Leads and Lags is a technique for?

A. Estimate Activity Resources

B. Sequence Activities

C. Estimate Activity Durations

D. Develop Schedule

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/05/05
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The Convenient Answer Option D - Develop Schedule.

MICHAIL KOSTOUROS  PMP PMI-RMP
by MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

Leads and lags is a tool and technique when we sequence activities but Adjusting leads and lags is a technique  when we develop schedule and we want also to optimize it. So the best answer is D.  

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. My opinion is option D.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B. Sequence Activities

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

 I Agree answers Option D

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion option D

 

 

Lead and  Lags: Since the improper use of leads or lags can distort the project

schedule, the leads or lags are adjusted during schedule network analysis to develop a viable

project schedule. Tools and Techniques for Develop Schedule are: Mathematical

analysis,Duration compression,Simulation,Resource -leveling ,Project management

software,Adjusting Leads and Lags and Coding structure

Javad Taghavi
by Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

The righ answer is option B

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

i agree the answer  D

More Questions Like This