(which include one dummy activity). Select the correct statement from the following:
A. This is invalid because nodes cannot have both dummy inputs and dummy outputs.
B. This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
C. This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.
D. This is a invalid because the number of outputs must equal the number of inputs.
E. This is a valid representation if the logic is correct.
Option E is the correct answer.
E. This is a valid representation if the logic is correct. The planning can be validated by creating a correct logic.
B. This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
In CPM, there can be dummy activities. My answer is E.
E. This is a valid representation if the logic is correct.
In my E. This is a valid representation if the logic is correct.
the answer is (E) if the logic is correct there is no problem
________Thank you for the invitation
Agreed with Option E_________
I am not sure of the answer but none the less thanks for the invite.
option E ............................................