It is useful to conduct project risk assessment according to the project's?

A. network

B. Work Breakdown structure

C. statement of work

D. charter

E. budget

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/05/18
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option B

With greetings and appreciation

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is B

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given, my first preference is option D - Charter ( Project Charter which tells us about the high level risks and risks based on what is and what is not included in the project ) . whereas WBS is used in identifying potential risks at both Micro & Macro level.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the correct choice.