Register now or log in to join your professional community.
A. All of the other alternatives apply.
B. is required before funding of the project by the project sponsor.
C. allows for data collection and analysis and progress reporting against which standards of performance can be measured.
D. is accomplished by selection of measurable variables against which performance can be judged.
E. Both1)allows for data collection and analysis and progress reporting against which standards of performance can be measured, and2) is accomplished by selection of measurable variables against which performance can be judged.
In order to create of the Project Objectives need to confirm Option E - Which collects between two options C & D.
In myn opinion - E. Both1)allows for data collection and analysis and progress reporting against which standards of performance can be measured, and2) is accomplished by selection of measurable variables against which performance can be judged.
Thank you for the invitation
I agree the option E
I agree with Option E as the correct choice.
B. is required before funding of the project by the project sponsor.
Before creation of project objectives, funding is required. The project objective describes the project's outcomes: intended and direct, short- and medium-term effects on the target group