How to create a robust master schedule?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/05/30
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

There are a number of different steps but the five I would choice are

  1. Define the work packages with a WBS,
  2. Work out the dependencies between these packages,
  3. Work out the duration of each package,
  4. Complete the critical path analysis,
  5. Resource load the plan and optimize to meet the success criteria. A paragraph on each of these should pass.