Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to?

deal with this negative risk event using which of the following outputs of Risk Monitoring and Control?

A. Additional risk identification

B. Corrective action

C. Workarounds

D. Risk management plan updates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/03
Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option C - Workaround. Workarounds are unplanned responses.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In myn opinion -  C. Workarounds

Explanation:  

Workarounds are unplanned responses. Workarounds deal with negative risk events as they

occur. As the name implies, workarounds were not previously known to the project team. The risk event was unplanned, so no contingency plan existed to deal with the risk event, and thus it required a workaround.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.