Register now or log in to join your professional community.
A. The burdened labor rate of the line organization average salary.
B. The burdened labor rate of the company average salary.
C. The burdened labor rate of the average salary of the project team members.
D. The burdened labor rate of the actual employees who performed the work.
E. None of the other alternatives apply
D. The burdened labor rate of the actual employees who performed the work.
It seems it should be Option D - based on The burdened labor rate of the actual employees who performed the work.
Option D is the correct choice.