Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process?

The WBS changes might in turn  require which of the following?

A. Scope changes

B. Schedule revisions

C. Risk response changes

D. Cost changes

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/03
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The correct answer is B.

B. Schedule revisions

Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option B - Schedule revision is required.

B. Schedule revisions -------------------

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option B

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the best choice.