Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Fast-tracked projects awarded and begun before all planning and risk assessment information is complete and available may?

A. Both1) be completed in reduced overall time than other projects, and2) be in a higher risk

category than other projects.

B. be completed in reduced overall time than other projects.

C. not be compatible with project risk and assessment

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/03

A. Both1) be completed in reduced overall time than other projects, and2) be in a higher risk

Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A is the correct answer

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation 

Agree answer Option A

 

ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The correct answer is A.

A.  Both1) be completed in reduced overall time than other projects, and2) be in a higher risk category then other proejcts.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given option - A appears to be most appropriate & thanks for the invite. 

More Questions Like This