You performed this project under contract. You are in the Contract Closure process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique you used to perform this function?
A. Performance audits
B. Performance reviews
C. Procurement audits
D. Procurement reviews
C. Procurement audits -----------------------
Answer is C - Procurement Audits where procurement contract & processes are reviewed normally by procurement & project manager before closing the procurement / contract and thanks for the invite.
D. Procurement reviews --------------