Register now or log in to join your professional community.
A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level-two assignments should be made.
B. The WBS breaks the project deliverables down to the work package level, where product analysis can be documented.
C. The WBS breaks the project deliverables down to the work package level, where cost and time estimates can be easily determined.
D. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified.
Option C is the correct answer.
C. The WBS breaks the proejct deliverables down to the work package level, where cost and time estimates can be easily determined.
Explanation: Option C
The work package level is the lowest level in the work breakdown structure. Schedule and cost estimates are easily determined at this level.
As name suggest WBS - Work Breakdown Structure, the purpose of preparing WBS of any project is to drill down to the lowest possible level to have a good understanding of the project. Thereby we can work out cost, time and resource requirements.
So answer "C" is correct.
Follower for our colleagues answers.
option C and option D ............................