Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The Work Breakdown Structure (WBS) is the basis for communicating?

A. Project budget, schedule, risk factors, work assignments.

B. Project objectives, dependencies, plan, cost control

C. Project scope, quality, schedule, dependencies

D. Project scope, schedule, staffing, cost control

E. Project scope, cost control, schedule, quality

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/17
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

My answer is E.

E. Project Scope, Cost Control, Schedule, Quality

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Project scope, cost control, schedule, quality

C. Project scope, quality, schedule, dependencies

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The convenient Answer is Option E -  Project scope, Cost control, Schedule & Quality. All Decompostion has to be achieved by teamwork of the project.

More Questions Like This