A. At the conclusion of the Develop Project Charter process
B. Prior to beginning the Develop Project Charter process
C. Prior to beginning the Planning processes
D. Prior to beginning the Preliminary Scope Statement process
My answer is for option (C) --------------
My awnser will be [c] Prior to beginning the planning processes.
Project Manager didnot involve in A B and D, he only involved in option C
Th project manager should be selected during Initiating phase of the project since he has to develop the porject charter ,identify the stakeholders etc
Thank you for the invitation
Agreed with Option C
With greetings and appreciation
C. Prior to beginning the Planning processes
Explanation: According to the PMBOK Guide, the project manager should be identified prior to beginning the Planning processes and is named and authorized in the project charter.