Early activities are detailed and future activities are still at a high level is called?

A. scope verification

B. progressive elaboration

C. stratagic elaboration

D. stratagic planning

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/18
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. progressive elaboration

Explanation: progressive elaboration: Early activities are detailed and future activities are still at a high level. < li >As an example, a software development project will start off with a detailed plan for Requirements Gathering phase, but other plans, such as testing plans, may not yet have the same amount of detail