ADM is an activity-on-arrow method. In this method, a dummy activity?

A. Identifies customer team meeting dates.

B. Shows slack.

C. Denotes a critical path relationship.

D. Denotes any dependency relationship.

E. Identifies customer deliverables dates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/18
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

My answer is D

D. Denotes any dependecy relationship

 

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option D 

With greetings and appreciation

MICHAIL KOSTOUROS  PMP PMI-RMP
by MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

D. Denotes any dependency relationship, and usually, in a graphical format should be presented  with dashed line and an arrow  head on one side

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Denotes any dependency relationship.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

i agree the option D

Gourab Mitra
by Gourab Mitra , Manager IT Project Program and Delivery Management(Full Time Contract/Consulting Role) , IXTEL(ixtel.com)

Agree with expert answers over here

rana yahya
by rana yahya , DevOps/Cloud Engineer , DECOIN(DTEB)

I agree with my fellows. ANSWER D

D. Denotes any dependency relationship