What is the difference between Bill of material and Material Take Off?

user-image
Question added by KARTHIKKUMAR NAGARATHINAM , Senior Piping Engineer , Adyard Abu Dhabi LLC
Date Posted: 2017/07/12
GANESH SHARMA
by GANESH SHARMA , construction manager , NASSER S AL HAJRI CORPORATION

A Material Take Off (MTO) is the process of analyzing all the drawings of a Project and determining all the materials required a Project. We then use the MTO  to create a bill of materials (BOM). From this BOM we order and procure materials