Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How to find plan vs actual in a P6 Schedule with out Cost Loading?

user-image
Question added by Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date Posted: 2017/07/22
MOHAMMAD BILAL
by MOHAMMAD BILAL , Planning Engineer , OCC

One method is expenses loading

Other is by duration % monitoring.

More Questions Like This