Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is F9 and Shift+F9 do in Primavera P6?

user-image
Question added by Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date Posted: 2017/07/22
Arun Malik
by Arun Malik , Planning Engineer , Fundament SPC

f9 is used for schedulling and shift+f9 used for resource levelling.

Suresh Edavana Parambadil
by Suresh Edavana Parambadil , Planning Engineer

F9 is used for scheduling the Primavera Programme

Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

F9 = Schedule only

Shift + F9 =Schedule + Level Resources

More Questions Like This