During which project management process are risk and stakeholder's ability to influence project outcomes the highest at the beginning of the process?

A. Initiating

B. Executing

C. Monitoring and Controlling

D. Planning

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/07/22
Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A is the correct answer.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation:

The Initiating process is where stakeholders have the greatest ability to influence outcomes of the project. Risk is highest during this stage because of the high degree of unknown factors.

 