lanes in each direction. You are interested in implementing a new project process called Design-Build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction at the same time the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of
A. fast tracking
B. managing the projects as a program
C. co-location
D. progressive elaboration
A. fast tracking ------------------