A. determining which tasks have the least amount of total slack.
B. subtracting the end date of task one from the start date of task two.
C. totaling the time for all activities.
D. determining the shortest path through the network.
E. Determining which tasks have the most slack
option A .........................................
Option (A) -------------------
Option A
The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration
A. determining which tasks have the least amount of total slack.