The critical path is calculated by?

A. determining which tasks have the least amount of total slack.

B. subtracting the end date of task one from the start date of task two.

C. totaling the time for all activities.

D. determining the shortest path through the network.

E. Determining which tasks have the most slack

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/07/22
Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

option A .........................................

Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A  

The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. determining which tasks have the least amount of total slack.