Register now or log in to join your professional community.
A. Critical Path adjusted by "high-risk" activity float.
B. highest risk path that contributes the most risk toward the project completion.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. the accumulated "expected' durations which maintain project completion.
A. Critical Path adjusted by "high-risk" activity float.