procurement plan for the program that will control the computer software lighting and screen projections during the concert. You've decided to contract with a rofessional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll opt for which contract type?
A. Fixed price plus incentive
B. Cost plus fixed fee
C. Fixed price
D. Cost plus incentive
C - Would be your answer for a better and lower risk.
The correct answer is option C -------------------
Explanation: Fied-price contracts have the highest risk to the seller and the least amount of risk to the buyer. However, the price the vendor charges for the product or service will compensate for the amount of risk they're taking on.