Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The most common types of schedules are Gantt charts, milestone charts, line of balance, and?

A. Calendar integrated activities.

B. Networks.

C. Both1) networks, and2) Calendar integrated activities.

D. Time phased events.

E. Both1) Time phased events., and2)Calendar integrated activities.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/07/28
Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

Option E .............................

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion optionB   ----------------------