Which of the following process involves measures project and product scope performance and managing scope baseline changes?

A. Collect Requirements

B. Define Scope

C. Verify scope.

D. Control scope

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/08/11
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation: Control scope process involves measures project and product scope performance and managing scope baseline changes.