Register now or log in to join your professional community.
costs associated with each level of expertise needed for the project:
A. Project Schedule Management Plan
B. Project Staffing Management Plan
C. Project Cost Management Plan
D. Project Quality Management Plan
Answer: B
Explanation: Based on the PMBOK, this information would be available in Staffing plan. The Cost management plan would contain cost of scheduled activities.
Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.