creating a list of prioritized risks describes which of the following processes?
A. Qualitative Risk Analysis
B. Quantitative Risk Analysis
C. Risk Identification
D. Risk Management Planning
Answer: A
Explanation: The purpose of Qualitative Risk Analysis is to determine what impact the identified risks will have on the project and the probability they'll occur. It also puts risks in priority order according to their effects on the project objectives and assigns a risk score for the project.