Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In an EPC project after how much percentage progress of civil work, should piping work be started?

user-image
Question added by Atul Pratap , Construction Manager , PUNJ LLOYD LTD.
Date Posted: 2017/08/19
karthick sankarabalan
by karthick sankarabalan , Construction Manager , Dodsal Engineering and Construction Pte Ltd

Piping work will start after completion of 50 % civil work .

Rajesh Pawar
by Rajesh Pawar , Sr. Project Manager , Toyo Engineering India Pvt. Ltd

Soil compaction and leveling shall be finished. Main Pipe rack installation work shall be started.

Mubeen Khalid
by Mubeen Khalid , QC Supervisor- Piping/Welding , National Petroleum Construction Company (NPCC)

We can start piping works after 30% complition of the civil work.

Fahim Shah
by Fahim Shah , Senior Project Engineer , Worleyparsons - Saudi Arabia

It should be after around 30%

It is not only Civil, but also structural works . The percentage progres should be about 25 to 28%

jaydip lathiya
by jaydip lathiya , Sr. Project Engineer. , Reliance project & Property Management and Services

We can start piping work after 30% of civil work completion.

More Questions Like This