In an EPC project after how much percentage progress of civil work, should piping work be started?

user-image
Question added by Atul Pratap , Construction Manager , PUNJ LLOYD LTD.
Date Posted: 2017/08/19
karthick sankarabalan
by karthick sankarabalan , Construction Manager , Dodsal Engineering and Construction Pte Ltd

Piping work will start after completion of 50 % civil work .

Rajesh Pawar
by Rajesh Pawar , Sr. Project Manager , Toyo Engineering India Pvt. Ltd

Soil compaction and leveling shall be finished. Main Pipe rack installation work shall be started.

Mubeen Khalid
by Mubeen Khalid , QC Supervisor- Piping/Welding , National Petroleum Construction Company (NPCC)

We can start piping works after 30% complition of the civil work.

Fahim Shah
by Fahim Shah , Senior Project Engineer , Worleyparsons - Saudi Arabia

It should be after around 30%

Raghuram Chityala
by Raghuram Chityala , Vice President , Reliance Industries Ltd

It is not only Civil, but also structural works . The percentage progres should be about 25 to 28%

jaydip lathiya
by jaydip lathiya , Sr. Project Engineer. , Reliance project & Property Management and Services

We can start piping work after 30% of civil work completion.