Register now or log in to join your professional community.
A. Develop the project charter
B. Develop the preliminary project scope statement
C. Collect Requirements
D. Develop the project statement of work
Answer: C
Explanation:
< li >After the project manager assigned to a project, Collect Requirements is started.
< li >Develop the project charter is before all of this.