In the initiation phase, project manager has been assigned to the project which process that must occur after this?

A. Develop the project charter

B. Develop the preliminary project scope statement

C. Collect Requirements

D. Develop the project statement of work

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/08/26
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

< li >After the project manager assigned to a project, Collect Requirements is started.

< li >Develop the project charter is before all of this.