in place should the risks occur. After some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. Although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. Which of the following is true regarding this question?
A. This is a positive response strategy.
B. This is a negative response strategy.
C. This is a response strategy for either positive or negative risk known as contingency planning.
D. This is a response strategy for either positive or negative risks known as passive acceptance.
Answer: D
Explanation:
This is a response strategy known as passive acceptance because the team has decided to take no action and make no plans for the risk. This is a strategy that can be used for either positive or negative risks.