Your team has identified the risks on the project and determined their risk score. The team is in the midst of determining what strategies to put?

 in place should the risks occur. After some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. Although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. Which of the following is true regarding this question?

A. This is a positive response strategy.

B. This is a negative response strategy.

C. This is a response strategy for either positive or negative risk known as contingency planning.

D. This is a response strategy for either positive or negative risks known as passive acceptance.

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2017/08/26
Muhammad Farooq
by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: D

Explanation:

This is a response strategy known as passive acceptance because the team has decided to take no action and make no plans for the risk. This is a strategy that can be used for either positive or negative risks.