A Work Breakdown Structure?

A. subdivides the project into manageable segments

B. both1) assures all work is identified and2) subdivides the project into manageable segments

C. assures all work is identified

D. All of the other alternatives apply.

E. provides the project sponsor with a time-phase task summary

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B ---------------------------