Which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder?

A. award Protest

B. any of the above processes can be used

C. bid protest

D. bid review

E. award review

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C -------------------------