Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Network schedules are prepared during the _ phase and updated during the _ phase?

 

A. Implementation, close-out.

B. Planning, finishing.

C. Development, close-out.

D. Conceptual, execution.

E. Development, implementation.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Conceptual, execution.     -----------------------------

More Questions Like This