Project Cost Management Plan is created as a part of?

A. Control Costs process

B. None of the other alternatives apply

C. Estimate Costs process

D. Determine Budget process

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/30
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Cost management plan: Describes how cost variances will be managed and Part of the overall project plan. Output of Estimate Costs process is: Cost estimates and Cost management plan