Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In the PDM, common constraints include?

 

A. Finish-to-finish

B. Start-to-start

C. Start-to-start, Finish-to-start and Finish-to-finish.

D. Finish-to-start and Finish-to-finish

E. Finish-to-start

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/30
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C -------------------------------