Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which is not correct about initial phase of a project?

A. The highest uncertainty is at this stage of the project.

B. The cost associated at the initial phase of the project is highest.

C. All of the other alternatives apply

D. Stake holders have maximum influence during this phase

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/07
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

minimum cost at the project initiation stage because minimum requirement of resources .

More Questions Like This