A. Estimate Activity Duration
B. Estimate Activity Resources
C. Develop Schedule
D. Sequence Activities
Answer: C
Explanation: Resource Levelling Heuristics: Allocate scare resources to critical path activities first etc. Tools and Techniques for Develop Schedule are: Mathematical analysis, Duration compression, Simulation,Resource -leveling ,Project management software, Adjusting Leads and Lags and Coding structure.