The "buy or make" decision is usually made during the?

A. pre-award cycle

B. acquisition cycle

C. contract evaluation cycle

D. requirements cycle

E. at any time that is convenient for the project manager

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/13
Sara Adel mahmoud mohmed
by Sara Adel mahmoud mohmed , كاشير , S.s.p egypt intrnational cairo airport

At any time that is convenient for the projeect manager

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. requirements cycle ----------------------