High level project constraints are determined during the _ process group?

 

A. closing

B. monitoring

C. initiating

D. executing

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/21
Pratap Kumar Atluri
by Pratap Kumar Atluri , Site Manager , Dutco Contracting Co LLC

C. HL constraints and assumptions will be made in project charter in Initiation phase.

Annabel Ekwere-Shallum
by Annabel Ekwere-Shallum , Process Design Engineer , Mobil Producing Nigeria Unlimited

C - High level project constraints will be determined during the Initiating Phase.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. initiating  ---------------------------------