Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the main purpose of project initiation?

A. Assign the project manager to the project.

B. Assign team members to project

C. Formally authorize the project.

D. Formally describe the project.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/21
Pratap Kumar Atluri
by Pratap Kumar Atluri , Site Manager , Dutco Contracting Co LLC

c. formally authorize the project. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: The main purpose of project initiation is Formally authorize the project.

More Questions Like This