What is the main purpose of project initiation?

A. Assign the project manager to the project.

B. Assign team members to project

C. Formally authorize the project.

D. Formally describe the project.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/21
Pratap Kumar Atluri
by Pratap Kumar Atluri , Site Manager , Dutco Construction LLC

c. formally authorize the project. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: The main purpose of project initiation is Formally authorize the project.