Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers.?

You performed this project under contract. You are in the Contract Closure process and know that you should document which of the following? (Choose the best response.)

A. Formal acceptance

B. Administrative closure procedures

C. Contract closure procedures

D. Product verification

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/28
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation: The project manager is responsible for documenting the formal acceptance of the work of the contract. This should be done during Contract Closure when projects are performed under contract or during Close Project if no work was performed under contract. In cases where part of the work was performed under contract and part with in-house staff, formal acceptance should occur in both of these processes.

More Questions Like This