Which of the following statements is true regarding the critical path?

 A. The critical path technique is the same as PERT. B. It allows for looping and branching. C. It should never be compressed. D. It's the duration of all tasks with zero float.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/09
Ryan Alaman
by Ryan Alaman , Project Engineer/Mechanical Engineer , US Army Corps of Engineers

D. It's the duration of all tasks with zero float.

C. it should never be compressed

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: You calculate the critical path by adding together the durations of all the tasks with zero float. The critical path can be compressed using crashing techniques.