Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires?

corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope because the glitch changed the characteristics of the product. Which of the following statements is true?

A. Changes to product scope are a result of corrective action.

B. Changes to product scope are reflected in the project scope.

C. Changes to product scope are reflected in the integrated change control plan.

D. Changes to product scope are a result of changes to the product description.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/09
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Changes to product scope should be reflected in the project scope.

More Questions Like This