The document that authorizes the release of organizational resources to the project is the _?

A. Charter

B. Statement of Work

C. Project Design Plan

D. WBS

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation: The Charter (contract) is the document that formalizes the project.