During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and?

 documented

A. Estimate Activity Duration

B. Define Activities

C. Sequence Activities

D. Develop Schedule

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Define Activities -----------------