What is the lowest level in a work breakdown structure?

A. Project task

B. Work package

C. None of the other alternatives apply

D. SOW

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/02
يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option B

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A work package is the lowest level of a work breakdown structur